Floating cranes, offshore cranes, offshore transfer cranes, deck cranes and other such equipment are core assets for heavy lifting operations. Their operational status directly impacts operational safety, personnel safety and property security. To eliminate safety hazards at the source and ensure the smooth progress of lifting operations, all operators must strictly comply with the following 8-step standardized inspection process, conduct checks one by one, and are strictly prohibited from skipping any steps or simplifying the inspection process.
Step 1: Inspection of Floating Crane/Offshore Crane Operation Environment and Site
1. Inspection Content: Operation water environment, meteorological conditions, surrounding obstacles, and mooring stability.
2. Inspection Standards: - Water area: No abnormal water flow (flow rate ≤ the upper limit specified by the equipment), no large amount of floating objects or submerged reefs, and water depth meets the draft and operation requirements of the floating crane. - Meteorology: Wind force ≤ the allowable operating wind force of the equipment (usually ≤ Level 6, refer to the equipment manual for specific requirements), no severe weather such as heavy rain, thunder and lightning, or heavy fog. - Surroundings: No unrelated ships, personnel, pipelines, buildings or other obstacles within the operation radius; obvious warning signs and warning areas are set up. - Mooring: Marine cranes, offshore cranes or deck cranes are firmly anchored, with evenly tensioned cables, no looseness or wear, and no obvious inclination of the hull or installation base.
3. Inspection Method: Observe the water environment, check the weather forecast (combined with on-site actual wind speed measurement), conduct a foot patrol within the operation radius, and inspect the anchoring system and cable status.
4. Confirmation Method: The on-site supervisor signs to confirm that the environment meets the operation requirements.
Step 2: Inspection of Floating Crane/Deck Crane Power System
1. Inspection Content: Engine, generator, hydraulic pump, fuel, and lubricating oil systems.
2. Inspection Standards: - Engine: No oil leakage, water leakage, or air leakage on the appearance; runs stably after starting, with no abnormal noise or vibration; instrument displays normal speed, water temperature, and oil pressure. - Generator: Output voltage and frequency meet standards; terminal blocks are firm without overheating; good grounding. - Hydraulic pump: No abnormal noise after starting; hydraulic oil pressure is stable within the specified range. - Fuel and lubricating oil: Fuel tank is sufficiently filled (≥ 80%); lubricating oil level is between the scale lines; oil quality is free from deterioration or turbidity; all pipeline joints are well sealed without leakage.
3. Inspection Method: Visually inspect the appearance and oil level; start the equipment to listen to the operating sound; check instrument data; touch the joints by hand to inspect the sealing condition.
4. Confirmation Method: The operator fills in the power system inspection record form, which is reviewed and signed by the safety officer.
Step 3: Inspection of Offshore Crane/Offshore Transfer Crane Lifting System
1. Inspection Content: Steel wire rope, hook, drum, brake, and limit device.
2. Inspection Standards: - Steel wire rope: No broken wires, broken strands, kinks or wear (wear amount ≤ 10% of the nominal diameter); sufficient lubrication; firmly fixed rope ends; intact anti-drop device. - Hook: No cracks, deformation or wear (wear amount of dangerous section ≤ 10%); intact anti-loosening device for hook nut; effective anti-drop pawl at the hook mouth. - Drum: No cracks or wear on the surface; steel wire rope is neatly arranged; intact rope guards at both ends of the drum. - Brake: Brake shoe and brake wheel are tightly fitted (contact area ≥ 70%); uniform brake clearance; sufficient braking torque; no slipping during braking. - Limit device: Lifting height limit and lowering depth limit are sensitive and reliable; can immediately cut off the power source when triggered.
3. Inspection Method: Visually inspect the status of the steel wire rope, hook and drum; measure the wear amount with a caliper; manually test the tightness of the brake; test the effectiveness of the limit device with no load.
4. Confirmation Method: The operator and safety officer conduct the inspection together, fill in the lifting system inspection record form and sign it.
Step 4: Inspection of Floating Crane/Offshore Crane Slewing and Luffing System
1. Inspection Content: Slewing bearing, slewing drive, luffing cylinder/winch, and luffing limit.
2. Inspection Standards: - Slewing bearing: No cracks or deformation on the appearance; firm and non-loose bolts; sufficient grease; stable slewing without jamming or abnormal noise. - Slewing drive: Motor or hydraulic motor operates normally; no oil leakage from the reducer; reliable slewing brake. -Luffing cylinder/winch: No leakage or deformation of the cylinder; no damage to the piston rod; steel wire rope of the winch is neatly arranged without wear; stable luffing action. - Luffing limit: Maximum and minimum luffing limit devices are sensitive; can stop the action in time when triggered.
3. Inspection Method: Visually inspect the appearance and connecting bolts; check the lubrication condition; operate the slewing and luffing actions with no load; test the limit device.
4. Confirmation Method: The operator conducts the practical operation inspection, which is verified and signed by the safety officer.
Step 5: Inspection of Deck Crane/Offshore Transfer Crane Control System
1. Inspection Content: Operating handle, control panel, instruments, communication equipment, and emergency stop device.
2. Inspection Standards: - Operating handle: Flexible operation without jamming or looseness; accurate return; normal correspondence of each action. - Control panel: Clear and intact indicator lights and buttons; reliable switch action; accurate instrument display (including weight display, angle display, etc.). - Communication equipment: Walkie-talkies and marine communication equipment have good signals and clear calls; can effectively communicate with commanders and surrounding ships. - Emergency stop device: Emergency stop buttons at all operating positions are sensitive and effective; can immediately cut off all power output when pressed.
3. Inspection Method: Operate each handle and switch one by one; check and verify instrument data; test communication equipment; press the emergency stop button to verify the effect.
4. Confirmation Method: The operator tests each item and records it; the on-site supervisor conducts spot checks and confirms.
Step 6: Inspection of Floating Crane/Offshore Crane Safety Protection Device
1. Inspection Content: Overload limiter, moment limiter, windproof device, fire-fighting equipment, and life-saving equipment.
2. Inspection Standards: - Overload limiter/moment limiter: Calibrated and qualified; can promptly issue an alarm signal and cut off the lifting or luffing action when simulating overload/over-moment conditions. - Windproof device: Windproof cables and anchoring devices of floating cranes, offshore transfer cranes and deck cranes are intact; can effectively fix the equipment to cope with sudden strong winds. - Fire-fighting equipment: Fire extinguishers are within the validity period, with normal pressure and sufficient quantity (configured according to equipment specifications), placed in a prominent and accessible position; fire hoses and nozzles are intact, with normal water pressure. - Life-saving
equipment: Life jackets, life buoys, life rafts, etc. are in sufficient quantity, intact and undamaged, and stored in a standardized manner.
3. Inspection Method: Start the limiter calibration procedure to test effectiveness; inspect the connection of windproof devices; check the validity period and pressure of fire-fighting equipment; count the quantity of life-saving equipment and inspect its status.
4. Confirmation Method: The safety officer leads the inspection, with the operator cooperating; fill in the safety device inspection record form and sign it.
Step 7: Inspection of Floating Crane/Offshore Crane Auxiliary Equipment and Tools
1. Inspection Content: Lifting rigging (shackles, slings, etc.), lighting equipment, maintenance tools, and emergency spare parts.
2. Inspection Standards: - Lifting rigging: Shackles have no cracks or deformation, and pin shafts are firm; slings have no damage or aging, with clear labels (indicating rated load) and meet the requirements of lifting heavy objects. - Lighting equipment: Operation area lighting, cab lighting and emergency lighting are intact, with sufficient brightness to meet the operation needs in night or dim environments. - Maintenance tools: Common tools such as wrenches, screwdrivers and pressure gauges are complete and intact; sufficient emergency spare parts (such as gaskets, fuses, etc.) are available.
3. Inspection Method: Visually inspect the status of lifting rigging and lighting equipment; count the quantity of tools and spare parts.
4. Confirmation Method: The operator checks each item one by one and fills in the auxiliary equipment inspection list.
Step 8: Inspection of Floating Crane/Deck Crane Operators and Technical Disclosure
1. Inspection Content: Operator qualification, operating personnel status, and safety technical disclosure.
2. Inspection Standards: - Operator qualification: Hold a valid operation certificate for floating cranes, offshore cranes, offshore transfer cranes or deck cranes, and be familiar with the performance and operation procedures of the operated equipment. - Operating personnel status: All personnel involved in the operation (including operators, commanders, and ground support personnel) are free from fatigue, intoxication, listlessness, etc., and wear personal protective equipment such as safety helmets and life jackets as required. - Safety technical disclosure: The on-site supervisor has conducted technical disclosure to all operating personnel, clarified the lifting weight parameters, operation process, risk points and emergency handling measures, and all personnel have signed for confirmation.
3. Inspection Method: Verify the operator's certificate; observe the status of the operating personnel; check the disclosure record and confirm the signature.
4. Confirmation Method: The on-site supervisor conducts a comprehensive inspection and signs the operation start confirmation form.
Requirements for Problem Handling and Recording - Any non-compliant issues found during the inspection must immediately stop the subsequent inspection and operation. The on-site supervisor shall organize the formulation of rectification measures, and clarify the rectification responsible person and rectification time. - After the rectification is completed, the problematic items must be re-inspected to ensure that the hazards are completely eliminated. The inspection process can only be continued after the re-inspection is qualified. - All inspection links must fill in the corresponding inspection record forms. The records must be true, accurate and complete, signed by the inspector and reviewer, and the record forms shall be archived and kept for at least 1 year. - If there are major hazards that cannot be rectified on site, they must be reported to the higher-level management department immediately, and risky operations are strictly prohibited.
why choose us
YFM has been focusing on marine machinery for 13 years. We have abundant practical experience and the necessary professional skills. We can provide you with a one-stop marine machinery product.
One-stop Solution
Our company's products, covering docks, decks, communication and other fields, have a complete range of products, which can be equipped in one stop to save your inquiry and procurement costs.
Rich experience
Our company has been deeply involved in the port industry for 13 years, and we have rich experience.
A comprehensive range of products
Our company's products include offshore cranes, dock hoppers, grapples, container spreaders, container tippers, etc.
Offer customized services
We can provide customized services for customers, if you have a project, we can also produce on your behalf.
Our clients
.